LEED BD+C: Core and Shell | v3 - LEED 2009

Bird collision deterrence

SSpc55 | Possible 1 point


Reduce bird injury and mortality from in-flight collisions with buildings.


Comply with the “Building façade and site structures,” “Exterior lighting,” and “Performance monitoring plan” requirements below.

Building façade and site structures

Develop a building façade and site design strategy to make the building and site structures visible as physical barriers to birds.

If all materials on the building façade have a Threat Factor of 15 or below, the project is exempt from the building façade requirements and the following Bird Collision Threat Rating calculations are not required. If any material on the building façade has a Threat Factor above 15, then the Bird Collision Threat Factor Rating calculations are required.

All other structures on the site, including, but not limited to handrails, guardrails, windscreens, noise barriers, gazebos, pool safety fencing, bus shelters, band shells, etc. must be constructed entirely of materials with a threat score value of 15 or less.

Steps for calculating the Bird Collision Threat Rating (BCTR)
First separate each building facade into Façade Zone 1 and Façade Zone 2. Façade Zone 1 includes the first 36 feet above grade, measured from grade at all points, as well as 12 feet above any green roof. Façade Zone 2 includes all façade areas above 36 feet. Establish total areas for Façade Zone 1, Façade Zone 2 and for the Adjusted Building Façade Area. Then identify the Material Types present on each façade, the corresponding Threat Factor of each material (for detailed types and associated threat factors, see the Bird Collision Deterrence Material Threat Factors developed by the American Bird Conservancy), and the total area of each Material Type. Lastly, establish the Factored Area for each Zone.

No more than 15% of the facade area in Façade Zone 1 can have a Threat Factor higher than 75. This area is quantified separately as the Hazardous Glazing Factor (HGF) in the calculator. However, more than 15% of the glazed area in Zone 2 may have a Factor higher than 75. All glazed corners or fly-through conditions must have a Threat Factor less than or equal to 25.

Table 1: General material types: threat potential

Material Type
Greatest Threat Potential Glass: Highly reflective and/ or completely transparent surface
Glass: Reflective or transparent surface interrupted by a visible pattern based on the 2 x 4 Rule*.
Glass: Reflective or transparent surface shielded by screens, shutters, or louvers where the resultant exposed glass satisfies the 2 x 4 Rule*.
Glass: Translucent with matte or textured surface
Least Threat Potential Opaque surface
*The 2 x 4 Rule is defined as a collision deterrence module based upon the physical profile of a bird in flight. Current research has established maximum module dimensions of 2” high x 4” wide.

Using the formulas below, achieve a maximum total building Bird Collision Threat Rating (BCTR) of 15 or less.

For each Façade Zone, calculate the Factored Area:
[(Material Type 1 Threat Factor) x (Material Type Area)] + [(Material Type 2 Threat Factor) x (Material Type Area)]… = Façade Zone Factored Area

Determine the Adjusted Building Façade Area:
[(2 x Zone 1 Area) + Zone 2 Area] = Adjusted Building Façade Area

Calculate the total building Bird Collision Threat Rating by dividing the sum of Zone 1 and Zone 2 Factored Areas by the Adjusted Building Façade Area:
(Zone 1 Factored Area + Zone 2 Factored Area) / Adjusted Building Façade Area = Total Building BCTR


Interior lighting

Limit the total duration of all nighttime lighting programmed ‘on’ to less than 90 minutes per day. Manual override capability may be provided for occasional after-hours use.


Reduce the amount of uplight leaving the building. Any suspended, wall or floor mounted luminaires with a direct line of sight above the horizon, thru any glass windows, skylights or doors must be automatically controlled to turn ‘off’ during all nighttime hours (the time between sunset and sunrise).


Have in place automatic window shades or shielding that limits light transmittance to 10% or less during the nighttime.

Implement a program to ensure that the lighting control system is being properly used to adjust lighting levels during all nighttime hours (the time between sunset and sunrise). .


Exterior lighting

Exterior building fixtures that are not necessary for safety, building entrances, and circulation shall be automatically shut off from midnight until 6 a.m. Manual override capability may be provided for occasional after-hours use.

In addition, meet these requirements for all exterior luminaires located inside the project boundary (except those listed under “Exemptions”), based on the following:

  • The photometric characteristics of each luminaire when mounted in the same orientation and tilt as specified in the project design; and
  • The lighting zone of the project property (at the time construction begins). Classify the project under one lighting zone using the lighting zones definitions provided in the Illuminating Engineering Society and International Dark Sky Association (IES/IDA) Model Lighting Ordinance (MLO) User Guide.

Do not exceed the following luminaire uplight ratings, based on the specific light source installed in the luminaire, as defined in IES TM-15-11, Addendum A.

Table 2. Maximum uplight ratings for luminaires

MLO lighting zone Luminaire uplight rating
LZ0 U0
LZ1 U1
LZ2 U2
LZ3 U3
LZ4 U4

Exemptions from the exterior lighting requirements
The following exterior lighting is exempt from the requirements, provided it is controlled separately from the nonexempt lighting:

  • specialized signal, directional, and marker lighting for transportation;
  • government-mandated roadway lighting;
  • hospital emergency departments, including associated helipads; and
  • lighting for the national flag in MLO lighting zones 2, 3, or 4.


Performance monitoring plan

Develop a three-year post-construction monitoring plan to routinely monitor the effectiveness of the building and site design in preventing bird collisions. Include methods to identify and document locations where repeated bird strikes occur, the number of collisions, the date, the approximate time, and features that may be contributing to collisions. List potential design solutions and provide a process for voluntary corrective action.

General Pilot Documentation Requirements

Register for the pilot credit

Credits 1-14

Credits 15-27

Credits 28-42

Credits 43-56

Credits 57-67

Credits 68-82

Credits 83-103

Credit Specific: BD+C

Building façade and site features

  • For materials on the building and site with a Threat Factor of 15 or below, submit a narrative describing why the materials, and building in general, are “bird-friendly.” Include a material list and supporting data.
  • A completed Bird Collision Threat Rating spreadsheet
  • Plan(s) and/or elevation(s) depicting the location of all materials and shading/screening devices used to comply with this credit
  • Applicable specification details on all materials and shading/screening devices used to comply with this credit

Exterior lighting

  • Site lighting plan with boundaries, elements, location of fixtures, lighting zone, and applicable measurements
  • Luminaire schedule showing uplight ratings, nighttime off-time durations for a typical day, and manual override capability

Performance monitoring plan

  • A copy of the post-construction monitoring plan
  • 10/16/2015:
    Expanded the applicability to all rating systems
    Added site features (site structures with glass) to the credit
    Adjusted and simplified the “Bird Collision Threat Rating” calculation
    Simplified the lighting requirements
    Adjusted the documentation based on the above changes to Requirements
    Miscellaneous edits to the background information, for reference
Join LEEDuser

Ask questions, share tips, and get notified of new forum posts by joining LEEDuser, a tool developed by BuildingGreen and supported by USGBC!

  • Share on Twitter
  • Share on Facebook
  • Share on LinkedIn
  • Print to PDF
Sample forms

No sample form available for this credit.

View all sample forms

2 commentsLeave a comment

President, BuildingGreen, Inc.

The "OR" headings and "AND" headings in the language are all at the same indent level, so it's hard to tell which are options and which are requirements. Can you please clarify?

Technical Director, LEED, U.S. Green Building Council

Thanks Nadav, we're working on formatting now. Requirements under options will be indented.

Select your preferred way to display the comments and click "Save settings" to activate your changes.

Leave a comment Don't have an account? Create one

You must be signed in to leave a comment.