Intent
Through a systematic process, to develop an understanding of the operation of the building’s major energy-using systems, options for optimizing energy performance and a plan to achieve energy savings.
Requirements
Option 1. Commissioning Process
- Develop a retrocommissioning, recommissioning or ongoing commissioning plan for the building’s major energy-using systems.
- Conduct the investigation and analysis phase.
- Document the breakdown of energy use in the building.
- List the operating problems that affect occupants’ comfort and energy use, and develop potential operational changes that will solve them.
- List the identified capital improvements that will provide cost-effective energy savings and document the cost-benefit analysis associated with each.
OR
Option 2. ASHRAE Level II Energy Audit
- Conduct an energy audit that meets the requirements of American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE), Level II, Energy Survey and Analysis.
- Document the breakdown of energy use in the building.
- Perform a savings and cost analysis of all practical measures that meet the owner’s constraints and economic criteria, along with a discussion of any effect on operations and maintenance procedures.
- List the identified capital improvements that will provide cost-effective energy savings and document the cost-benefit analysis associated with each.