Additional commissioning

EAc3 | Possible 1 point

Intent

Verify and ensure that the entire building is designed, constructed and calibrated to operate as intended.

Requirements

In addition to the Fundamental Building Commissioning prerequisite, implement the following additional commissioning tasks:

  1. Conduct a focused review of the design prior to the construction documents phase.
  2. Conduct a focused review of the Construction Documents when close to completion.
  3. Conduct a selective review of contractor submittals of commissioned equipment. (The above three reviews must be performed by a firm other than the designer.)
  4. Develop a recommissioning management manual.
  5. Have a contract in place for a near-warranty end or post occupancy review.
Join LEEDuser

Ask questions, share tips, and get notified of new forum posts by joining LEEDuser, a tool developed by BuildingGreen and supported by USGBC!

  • Share on Twitter
  • Share on Facebook
  • Share on LinkedIn
  • Print to PDF
Sample forms
View sample forms

0 commentsLeave a comment

Leave a comment Don't have an account? Create one

You must be signed in to leave a comment.