Our deadline to respond to our preliminary comments or appeal is coming to an end and we need more time. Can we have an extension?

Answer

The 25 business day duration stated in our emails when we return a review to the project team is a suggestion that is intended to encourage project teams to maintain progress. We appreciate your letting us know if you will need more time. Please take the time you need to prepare a thorough response to review comments, or to prepare your appeal. Please note, all O+M projects are subject to all performance period criteria, and this information is only relative to clarifications between rounds of review.

Can't find what you're looking for?

Ask a question

Have a question or comment?

800-795-1747

(within U.S.)

202-742-3792

(outside U.S.)

M-F 9:00 AM to 5:30 PM EST


Billing

U.S. Green Building Council
P.O. Box 404296
Atlanta, GA 30384-4296


Location

2101 L Street, NW
Suite 500
Washington DC 20037
Map