Created on LEED Interpretation

ID#

li-10333

Credit NameSSc1 - Site stewardship
Credit CategorySustainable sites
International ApplicableYes
Campus ApplicableNo

Rating System

LEED BD+C: Homes, LEED BD+C: Multifamily Midrise

Rating System Version

v3 - LEED 2008

Inquiry

SS 1.1 (a) requires the stockpiling and protection of topsoil. In mass graded subdivisions, builders are frequently building on lots brought to rough grade by a developer who is not the builder. The soil used to achieve rough grade is not topsoil. If there is no topsoil on the site and the original developer did not stockpile the topsoil for reuse, how is this prerequisite to be met?