Created on LEED Interpretation

ID#

li-10345

Credit NameEAc10 - Renewable energy
Credit CategoryEnergy & atmosphere
International ApplicableYes
Campus ApplicableNo

Rating System

LEED BD+C: Homes

Rating System Version

v3 - LEED 2008

Inquiry

The Mid-rise Guidelines for California indicate that the calculation should compare estimated renewable electricity production to TOTAL energy loads for the Standard Design building. This differs from EA 10 for low-rise buildings, where the estimated renewable electricity production is only compared to the electricity loads (not total energy loads) for the Standard Design building. Which is correct for mid-rise buildings in California?