ID#
li-10389
| Credit Name | EAc4 - On-site and off-site renewable energy |
|---|---|
| Credit Category | Energy & atmosphere |
| International Applicable | Yes |
| Campus Applicable | No |
Rating System
LEED BD+C: New Construction, LEED BD+C: Core and Shell, LEED BD+C: Schools, LEED BD+C: Retail, LEED BD+C: Healthcare, LEED ID+C: Commercial Interiors, LEED ID+C: Retail, LEED O+M: Existing Buildings
Rating System Version
v3 - LEED 2009, v3 - LEED 2008, v2 - Schools 2007, v2 - LEED 2.2, v2 - LEED 2.1, v2 - LEED 2.0
Inquiry
The project team is planning on installing a Cogeneration System that will take Biogas and turn it into Electricity to be used wholly on-site. The heat produced by this Cogeneration system will also fully be used on-site to preheat heating hot water and domestic hot water via a heat exchanger and potentially to power an absorption chiller.\n\nThe building will receive the Biogas from a local Biogas provider and plans to enter into at least a 10 year contract with this provider to supply enough Biogas to the building to fully power the planned Cogeneration system. The contract will stipulate both that enough Biogas will be fed into the pipeline to meet required demands of the Cogeneration system and that the Biogas will be metered to prove that the actual amount of Biogas supplied meets the contracted requirements at all times.\n\nThough the Biogas is not being piped exclusively to the site (contractually it is supplied exclusively via project ownership funds), it is transported directly to the site in the existing natural gas pipeline. This approach achieves the exact same net result on the Natural Gas grid as piping Biogas exclusively to the project site in its own dedicated pipeline and allows the project to avoid having to dig up 100s of miles of land and lay a brand new pipeline to the project, something that would have a significantly detrimental effect on the local environment. In an urban environment like where the project is located, there is little or no option to be able to refine and extract Biogas on-site or even very close to a site, so the approach the project team is suggesting is the best and most reasonable alternative.\n\nIs this approach acceptable in accordance with the Reference Guide and Addendum 100001081 (November 1, 2011)?