ID#
li-2112
| Credit Name | EAc1 - Optimize energy performance |
|---|---|
| Credit Category | Energy & atmosphere |
| International Applicable | No |
Rating System
LEED BD+C: New Construction, LEED BD+C: New Construction, LEED BD+C: Schools, LEED BD+C: Schools, LEED ID+C: Commercial Interiors, LEED BD+C: Core and Shell, LEED O+M: Existing Buildings
Rating System Version
v2 - LEED 2.2, v3 - LEED 2009, v2 - Schools 2007, v3 - LEED 2009, v3 - LEED 2009, v3 - LEED 2009, v3 - LEED 2009
Inquiry
This Project involves the construction of a Testing Facility for High Volume Low Velocity circulation fans. The building consists of a 1940 S.F. General Office Area, a 1940 S.F. Shop Area, and a 40550 S.F. Testing Area with a 50\' joist height. The Testing Area will have in it at most (4) four High Volume Low Velocity circulation fans operating at the same time. The building will have no transient occupants, and a maximum of (6) six employees that will occupy the entire building during normal business hours. This CIR is in reference to the Testing Area. 1. Testing Area: As part of the USGBC New Construction & Major Renovation Version 2.2, the building is required to meet ASHRAE 90.1 2004 (Energy Standard for Buildings Except Low-Rise Residential Buildings), and ASHRAE 62.1 2004 (Ventilation for Acceptable Indoor Air Quality). In accordance with ASHRAE 90.1 2004 the Testing Area is given a baseline LPD (Lighting Power Density) of 1.4 W/SF as is standard for a Laboratory. The only reference in ASHRAE 62.1 2004 (Ventilation for Acceptable Indoor Air Quality) with regard to a Laboratory is listed in Table 6-1 under "Educational Facilities" - "Science Laboratories". The classification that most closely matches the actual use of the space in the Testing Area for ventilation purposes is a Warehouse, since the population density is low (6760 SF/Person), and the area will never contain "Laboratory" chemicals, "Laboratory" exhaust hoods, Make-Up air or a population density on par with an Educational Facility Science Laboratory. The Ventilation and Exhaust requirements for a Science Lab are (3) three times that of a Warehouse, and subsequently (3) three times the energy cost. Since the "actual" usage of the Testing Area fits the lighting energy requirements of a Laboratory (ASHRAE 90.1 2004) and the ventilation requirements of a Warehouse (ASHRAE 62.1 2004), can the design team consider this space as such for calculations, or does the requirement to stay consistent with room classifications supersede actual building function?