ID#
li-2289
| Credit Name | MRc4 - Recycled content |
|---|---|
| Credit Category | Material & resources |
| International Applicable | Yes |
| Campus Applicable | No |
Rating System
LEED BD+C: New Construction, LEED ID+C: Commercial Interiors, LEED BD+C: Core and Shell, LEED BD+C: Schools
Rating System Version
v3 - LEED 2009, v2 - Schools 2007, v2 - LEED 2.2, v2 - LEED 2.0
Inquiry
The project team is seeking clarification for our intended use of on-site excavated rock. During excavation and site work at the project, a large amount of limestone rock was encountered. Instead of disposing of the rock off-site, we are using it on-site. We are breaking up the on-site rock into 12 - 18" pieces for use as rip-rap. This eliminates the need to use virgin quarry rock and reduces the amount of the volume of waste sent to the landfill. We would like to apply the market value of the rip-rap to MR credit 4.1, Recycled Content (pre-consumer). We will use the following formula for our calculations: # of Tons of excavated rock used on site * the local quarry price per ton * 1/2 = $ applied to MRc4.1 Since this approach will use what is typically a waste stream and use it to reduce the demand for off-site materials, it seems to meet the overall intent of the LEED process. If the rock cannot be applied to MRc4.1, is there any other credit that it could be applied to?