Created on LEED Interpretation

ID#

li-2320

Credit NameEQc3.2 - Construction IAQ management plan - after construction
Credit CategoryIndoor environmental quality
International ApplicableYes

Rating System

LEED BD+C: New Construction, LEED BD+C: New Construction, LEED BD+C: New Construction, LEED BD+C: Schools, LEED ID+C: Commercial Interiors, LEED ID+C: Commercial Interiors, LEED O+M: Existing Buildings, LEED O+M: Existing Buildings

Rating System Version

v2 - LEED 2.0, v2 - LEED 2.2, v2 - LEED 2.2, v2 - Schools 2007, v2 - LEED 2.0, v3 - LEED 2009, v2 - LEED 2.0, v3 - LEED 2008

Inquiry

The 9/5/2006 allows projects to provide both IAQ testing and building flush-out in different construction phases. We intend to provide IAQ testing and building flush-out in different areas of the building within the same construction phase. Our project is a high school addition/renovation that will be occupied in phases. The first phase of construction is complete and those spaces were tested, prior to occupancy, based on the credit ruling dated 10/8/2002. The second phase of the project includes a pool and academic spaces. We are concerned that the chemicals used in the pool will adversely impact the testing results. We therefore propose flushing out that space, using the \'purge mode\' on the pool\'s mechanical unit. Based on the 9/8/2004 credit ruling, we will achieve 14,000 cu ft of outdoor air per square foot of floor space in less than 5 days. As the rest of the Phase 2 areas will not meet the flush-out criteria prior to the scheduled occupancy, we therefore intend to provide IAQ testing in the remaining portions of the building. Until both the IAQ testing and the flush-out is complete, we will prevent cross-contamination between areas. Protection measures will follow the SMACNA Guidelines for Occupied Buildings as outlined in the Construction IAQ Management Plan. Please confirm if the proposed compliance path meets the credit intent. If it is not acceptable, please clarify what changes are required in order to meet the credit requirements.