Created on LEED Interpretation

ID#

li-3004

Credit NameMRc2.1 - Construction waste management - divert 50% from disposal
Credit CategoryMaterial & resources
International ApplicableYes

Rating System

LEED BD+C: New Construction, LEED BD+C: New Construction, LEED BD+C: New Construction, LEED BD+C: Schools, LEED ID+C: Commercial Interiors, LEED BD+C: Core and Shell

Rating System Version

v2 - LEED 2.0, v2 - LEED 2.2, v2 - LEED 2.2, v2 - Schools 2007, v2 - LEED 2.0, v2 - LEED 2.0

Inquiry

In accordance with Credit MR 2.1 and 2.2, the contractor is requesting an alternate method to divert landfill trash that can not be recycled. The contractor proposes to pay the additional cost to transport non recyclable trash to a power plant to be incinerated and converted into electrical energy. This effort will run in parallel and not reduce the commitment of sorting recyclable and reusable materials. Products that contain a mixture of materials that can not be separated for recycling are the type of materials proposed for incineration. The power plant proposed has approved EPA pollution control devices.