| Credit Name | MRc3.1 - Materials reuse - 5% |
|---|---|
| Credit Category | Material & resources |
| International Applicable | Yes |
Rating System
LEED BD+C: New Construction, LEED BD+C: New Construction, LEED BD+C: New Construction, LEED BD+C: New Construction, LEED BD+C: Schools, LEED BD+C: Schools, LEED ID+C: Commercial Interiors, LEED ID+C: Commercial Interiors, LEED BD+C: Core and Shell, LEED BD+C: Core and Shell
Rating System Version
v2 - LEED 2.0, v2 - LEED 2.2, v2 - LEED 2.2, v3 - LEED 2009, v2 - Schools 2007, v3 - LEED 2009, v2 - LEED 2.0, v3 - LEED 2009, v2 - LEED 2.0, v3 - LEED 2009
Inquiry
This credit inquiry seeks clarification on how to account for reuse of materials "harvested" from an existing building for reuse in the same building. By definition, on page 188 of the Reference Guide: "Salvaged materials are construction materials recovered from existing buildings and reprocessed for reuse in other buildings." This seems to imply that materials from an existing building cannot be counted as salvaged materials if they are reinstalled in the same building.\nOur project includes deconstruction of a number of building components with the specific intent of reprocessing them for reinstallation into the building. For example, about 11,000 board-feet of old-growth timbers were harvested from the demolition of existing roof framing. The wood was milled and used throughout the building for architectural millwork features. Clearly, reprocessing was almost total. Also, over two hundred (200) doors were removed, restored to their original finish, fitted for new hardware, and reinstalled. About half were reinstalled into different locations. Some reprocessing was required. A number of other components, such as tack boards, blackboards, and display cases, were harvested, protected and reinstalled into new locations. The only reprocessing was to recondition and reinstall the components.\nWe seek LEEDTM credit for the extensive salvaging work that was accomplished. To exclude the harvesting program we undertook seems an unintended consequence of the definition of salvaged materials. Can we include materials harvested from the building as salvaged materials? We have also considered the potential of applying for an Innovation credit for conducting a "harvesting" program. Is that a better approach?