Created on LEED Interpretation

ID#

li-5217

Credit NameEQc3.2 - Construction IAQ management plan: before occupancy
Credit CategoryIndoor environmental quality
International ApplicableYes
Campus ApplicableNo

Rating System

LEED BD+C: New Construction, LEED ID+C: Commercial Interiors, LEED BD+C: Schools

Rating System Version

v2 - Schools 2007, v2 - LEED 2.2, v2 - LEED 2.0

Inquiry

The total area 79,650 SF of the new building is divided as indicated below. 20,940 SF - Data Center with raised floor 13,200 SF - office space, loading, storage and support areas 45, 510 SF - MEP spaces --79,650 SF The data center (20,940 SF) and MEP spaces (45,510 SF) are designed with minimal outside air, which is not occupied by the office staff. The question is: would Performing a flush-out only in office spaces (20,940 SF), excluding the Data Center and MEP spaces shall meet LEED NC 2.2 Credit 3.2 requirements under flush out option? This question is being asked on the basis that only office spaces are truly occupied by the personnel, and data center and MEP spaces are not.