Created on LEED Interpretation

ID#

li-5418

Credit NameEAc2.1-2.3 - Renewable energy
Credit CategoryEnergy & atmosphere
International ApplicableYes

Rating System

LEED BD+C: New Construction

Rating System Version

v2 - LEED 2.0

Inquiry

We are proposing to provide rooftop PV panels sized to meet 5% of total load. Our building is approximately 60% laboratory and 40% office. Can we assume that the lab electrical loads are "process" and do not need to be included in total energy load? This ruling will significantly effect the size of our array and whether or not we will pursue the credit at all.