Created on LEED Interpretation

ID#

li-5463

Credit NameEAp1 - Fundamental building systems commissioning
Credit CategoryEnergy & atmosphere
International ApplicableYes

Rating System

LEED BD+C: New Construction

Rating System Version

v2 - LEED 2.0

Inquiry

According to LEED, we would like clarification on who can manage the contract for the Commissioning Authority. We are running into several cases where the client or owner wants to have the architect of record (who is also the design architect) handle the ComX contract. Sometimes the Owner is trying to get the ComX under a CM, At-risk CM or have the At-risk CM provide commissioning services to meet the EAp1. It is generally easier for public clients to run the Commissioning Authority through the architect, as they have all the contractual processes in place and it is easy to release "Additional Services" with the architect. Our reading of the LEED reference guide could infer that the ComX must be hired by the Owner. Is it more preferable that the Commissioning Authority be contracted by the Owner or through other entities associated with the project (with understanding that ComX is always independent/3rd party)?

Logging out the application..