Created on LEED Interpretation

ID#

li-5902

Credit NameSSp1 - Erosion and sedimentation control
Credit CategorySustainable sites
International ApplicableYes

Rating System

LEED BD+C: New Construction

Rating System Version

v2 - LEED 2.2

Inquiry

The project requires the demolition of existing buildings prior to any groundwork for new construction of the library. The owner is planning on contracting the demolition work separately from the construction work and there may be up to three months after demolition before construction will begin on the library. The question is: In seeking LEED certification for the construction of the new library building, that is only 25% of a larger development, can the Sustainable Sites prerequisite be met without regard to the manner in which the site is cleared under the separate demolition contract, or does the process of demolition need to meet the prerequisite for the project, as a whole, to qualify for certification?

Logging out the application..